The Patiala bypass bridge: who built it, who maintained it, who signed
A 60 m steel truss bridge on NH-07 collapsed over the Bhakra Main Line canal on 19 November 2026. NHAI says the Border Roads Organisation built it. NHAI's own records show who owned, inspected and paid for its upkeep after that.
Summary
- The Border Roads Organisation (BRO) built the bridge, about 2011, under Punjab PWD supervision. NHAI confirms this.
- NHAI has owned and maintained the bridge since 2018. NHAI says so in its own post on the day of the collapse.
- NHAI's maintenance contract for this stretch requires a quarterly inspection of every bridge for structural damage, and a detailed condition inspection before each monsoon.
- On the day, the maintenance contract was with M/s Gaurav Singh. NHAI awarded it at 43.77% below its own estimate. Every maintenance award on this stretch since 2022 was 36% to 44% below estimate.
- The 2024 contract's price list had no item to repair a steel truss. The only bridge item was expansion joints: 0.54% of the estimate.
- In September 2025 an NHAI engineer said the joints of this canal bridge needed "urgent rectification to ensure the structure's safety".
- We do not know what NHAI's bridge inspections found. Our questions to NHAI are in Section 10.
2. What NHAI said
3. Who built the bridge
4. Who maintained it, and who signed
5. What the contract required
6. What the contract paid for
7. Warnings before the collapse
8. Claims we checked
9. What we do not know
10. Right of reply
11. Method
Sources
1. What happened
At about 06:00 on 19 November 2026, the left-hand (LHS) span of a steel truss bridge fell. The bridge carries the Patiala bypass of NH-64 (new NH-07) over the Bhakra Main Line canal, near Pasiana village. Two trucks loaded with sand were on the span. One truck caught fire. Nobody died. At least one driver was hurt.
NHAI's Regional Office in Chandigarh posted a traffic advisory the same morning (Exhibit 1).
2. What NHAI said, and what it left out
At 12:40 NHAI posted a clarification (Exhibit 2). It says that BRO built the bridge under Punjab PWD supervision. It asks people not to spread "unverified or factually incorrect information".
The statement about the builder is correct. It does not say who looked after the bridge. Since 2018, inspection and repair of this bridge is NHAI's job, under NHAI's own contracts. Sections 4 to 7 show those contracts.
3. Who built the bridge
The bypass was a Defence project. In May 2005 the Ministry of Road Transport and Highways (MoRTH) accepted a Defence Ministry proposal. BRO was to build a Patiala bypass on NH-64 for Army traffic to the border. The estimate was Rs 37 crore. BRO's Project Chetak started work in 2007. The cost went up to Rs 110 crore. The contractor left midway. BRO missed six deadlines. The road opened in June 2015, in poor condition.
The steel truss over the canal was made by Traders & Engineers Pvt Ltd, Kolkata. The company's portfolio describes it as a "60 meters long (C/C of Abutment Bearings) Single Span Major PMT Bridge with Footpaths with Steel Truss Super Structure (Through Type) and Sub Structure on Pile Foundations over Bhakra Main Canal at Km 17.510 on road Patiala Southern Bye-Pass under Project Chetak". The company gives the date as 2011.
In 2015 the Punjab PWD took over the road and widened it to four lanes. NHAI's own project database records this work as an EPC contract (UPC N/05012/02002/PB, km 50.000 to 69.870). It was awarded on 11 March 2015 for Rs 305 crore and completed on 28 October 2016. The section went to NHAI in 2018.
4. Who maintained it, and who signed
NHAI does not maintain highways with its own staff. It gives short maintenance contracts to private contractors, and it appoints a supervision consultant to check their work. We found every such contract for this stretch in NHAI's award records on etenders.gov.in, with the letter of acceptance (LoA) for each one.
| Tender ID | Work | Contractor | Price | Below NHAI estimate | Letter date | LoA signed by (NHAI) |
|---|---|---|---|---|---|---|
| 2021_NHAI_81978_1 | Maintenance, km 50.000–69.280, 240 days | VMAKS Construction Pvt Ltd, Faridabad | ₹99,99,890 | 33.77% | 10 Sep 2021 | Priyanka Meena, GM (Tech) |
| 2022_NHAI_126864_1 | Maintenance, km 50.000–110.720, 24 months | M/s A S Patel, Modasa, Gujarat | ₹5,54,09,787 | 42.09% (of ₹9,56,82,588) | 18 Nov 2022 | Aashim Bansal, DGM (Tech) |
| 2022_NHAI_118523_1 | Supervision consultant, km 0–110.720, 3 years | MSV International Inc with Mahamarg Infra Consultant Pvt Ltd | ₹3,80,10,000 + GST | – | 24 Nov 2022 | Aashim Bansal, DGM (Tech) |
| 2024_NHAI_200504_1 | Maintenance, km 50.000–110.720, 12 months (2nd call) | M/s Kamdhenu Construction, Prayagraj | ₹2,64,12,139 | 35.99% (of ₹4,12,62,519) | 9 Sep 2024 | Aashish Garg, DGM (Tech) |
| 2025_NHAI_250918_1 | Maintenance, km 50.000–123.900, 1 year (in force on 19 Nov 2026) | M/s Gaurav Singh, Assandh, Haryana | ₹9,89,07,329 | 43.77% (of ₹17,58,97,793) | 15 Dec 2025 | Vipon Kumar, DGM (Tech) |
| 2025_NHAI_246021_1 | Supervision consultant, km 0–110.720, 3 years | Lion Engineering Consultants Pvt Ltd with Hadimba Consultants | ₹4,91,43,500 + GST | – | 25 Mar 2026 | Vipon Kumar, DGM (Tech) |
Every letter says: "This issue with the approval of RO Chandigarh". The Regional Officer of NHAI Chandigarh approved each award.
A low price is legal. NHAI awards the work to the lowest valid bid. But a contract at 44% below the estimate pays for much less work than NHAI planned. NHAI must then make sure that the inspections are still done.
Were there gaps in cover?
Figure 3 shows each contract from its letter date. The real start dates are not public, so the gaps are approximate.
5. What the contract required
The maintenance contract tells the contractor what to inspect and how often. These are the clauses from the 2024 contract for this stretch (km 50.000 to 110.720).
The contract also says: "Repairs arising out of the inspections shall be carried out by the Contractor [...] after a joint assessment with the Engineer and approval of NHAI." So the inspection results must reach NHAI. The supervision consultant also has a named Bridge/Structural Engineer in each contract. In April 2025 NHAI also told its project directors to rate every bridge twice a year (policy circular 6.41/2025, as reported).
The contract requires these inspections. We ask NHAI to publish the reports.
6. What the contract paid for
A maintenance contract pays item by item, from a price list called the bill of quantities (BOQ). We read the BOQ of the 2024 contract (estimate ₹4,12,62,519) line by line. Figure 4 groups the 38 items.
| Item | Description (NHAI's words, shortened) | Quantity | Amount (₹) |
|---|---|---|---|
| A3 | Cleaning of carriageways, footpaths, verges, expansion joints, drainage spouts of bridge (twice a year) | 25,100 m | 12,55,000 |
| A10 | Providing and installation of damaged strip seal expansion joint [...] for bridge | 50 m | 2,23,214 |
| B3 | Painting with synthetic enamel paint on old wood work or metallic or plastered or concrete surface | 42,720 sqm | 24,41,021 |
| A11 | 6 to 8 mm microsurfacing (road surface) | 40,000 sqm | 57,60,000 |
| C8 | Road marking with hot applied thermoplastic | 8,640 sqm | 47,57,184 |
The table shows the bridge-related items next to the two largest road items. NHAI could repair the truss under a separate contract. We searched NHAI tenders from 2017 to November 2026 on etenders.gov.in. We found no NHAI Chandigarh tender for a bridge inspection, structural audit, condition survey or load test on this road.
7. Warnings before the collapse
September 2025: "urgent rectification"
On 20 September 2025 The Tribune reported that NHAI closed one side of the bridge over the canal at the 68-km mark for two to three weeks.
"The expansion joints [...] have been found damaged and require urgent rectification to ensure the structure's safety." NHAI Superintending Engineer Abhishek Chauhan, as reported by The Tribune, 20 September 2025.
The closed side was Sangrur to Chandigarh. On NHAI's chainage that is normally the right-hand carriageway. The span that fell is the left-hand one. We ask NHAI which side it repaired and what else the inspection found.
2022: another BRO steel truss on the same bypass needed a new superstructure
The bypass has a second, smaller steel truss: a 41.5 m "minor bridge" over a stream at km 60.682 (62+645 in some NHAI documents). In 2022 NHAI decided to demolish and rebuild its deck slab and superstructure. NHAI cancelled the first tender "due to administrative reasons", widened the scope, and awarded the work to M/s N.B. Construction Company, Kaithal, for ₹1,45,93,019 (letter of 17 January 2023).
In 2022 NHAI found that one BRO-era truss on this road needed a new superstructure. We found no record that NHAI checked the larger truss over the canal in the same way.
8. Claims we checked
| Claim | Verdict | Why |
|---|---|---|
| "NHAI built the bridge in 2016" (several news sites) | False | BRO built the truss about 2011. The four-laning by Punjab PWD finished in October 2016 (Section 3). |
| NHAI: BRO built it under PWD supervision | Incomplete | Correct about the builder. It leaves out that NHAI has owned and maintained the bridge since 2018 (Sections 4–6). |
| "The bridge was 60 m long" | True | NHAI's advisory; the steel contractor's record (60 m between bearings). |
| "It was a Bailey bridge" | False | A Bailey bridge is a temporary panel bridge. This was a permanent through-type truss on pile foundations. |
| "The trucks fell into the canal" | False | The trucks stayed in the fallen span. |
| "No casualties" / "several injured" | Both partly true | Nobody died. At least one driver was hurt. |
| "Overloaded sand trucks caused it" | Not proven | The Deputy Commissioner, citing NHAI's first report, said a truck broke down mid-span and two more stopped behind it. No truck weights and no load limit for the bridge are public. |
| "Built in 2000" | Probably false | BRO started the bypass in 2007. |
| "Handed to NHAI in 2021" | Conflicts | NHAI says 2018. NHAI's maintenance tenders for this section start in December 2020. |
| "A magisterial inquiry was ordered" | Partly reported | Four outlets report an inquiry by the district administration. Only Aaj Tak says "magisterial". We have not seen an order. |
| Old pictures of a "Bhakra canal bridge collapse" | Check | A village bridge at Shutrana collapsed on 17 Oct 2025. It is a different event. |
9. What we do not know
- NHAI's inspection reports and condition rating for this bridge since 2018, and who signed them.
- Who maintained the stretch from about September to December 2025, and who supervised it from about November 2025 to March 2026.
- The 2018 handover record: the joint inspection and the list of defects.
- What else the September 2025 inspection found, and which side NHAI repaired.
- The design load of the bridge, any posted load limit, and the weights of the trucks.
- The content of NHAI's report to the Deputy Commissioner on 19 November.
MoRTH's bridge database (IBMS) keeps a condition rating for national highway bridges. Its data needs a login. We did not try to get past the login.
10. Right of reply
We are sending the questions in Section 9 to NHAI Regional Office Chandigarh. We are asking M/s Gaurav Singh, Lion Engineering Consultants, MSV International, M/s Kamdhenu Construction and M/s A S Patel two questions. Which bridge inspections did they do on this stretch? What did they report to NHAI? We are asking BRO, Punjab PWD and Traders & Engineers Pvt Ltd to confirm the construction details. We will publish every answer here, in full or in fair summary, with the date.
11. Method
We used only public records. We did not use any login, bot check bypass or private source.
Data
- NHAI tender archive. S1D Labs keeps a copy of NHAI's tender pages and documents (nhai.gov.in). We found 52 tenders for this corridor from 2020 to 2025 and read their notices, RFPs, schedules, drawings and price lists.
- etenders.gov.in award records. Our copy has 303,522 tenders. For each contract we read the award record, the technical and financial summaries and the letter of acceptance.
- NHAI lists. NHAI's lists of awarded works (FY 2021-22 to 2024-25) and of works "balance for award" (1 March 2026). NHAI's Project Information page for the four-laning record.
- NHAI map layers. NHAI's road-accident (blackspot) layer and its "distress bridges" layer (datalakew.nhai.gov.in). This bridge is not in the public distress layer.
- Other records. CPPP (BRO tender 2013_BRO_1843_1), the MCA company register, contractor registers (CPWD, PMGSY), the steel contractor's website, and news reports from 2005 to 2026.
Steps
- We placed the bridge. We matched NHAI's chainages, the accident map point near Passiana, the steel contractor's km 17.510 and the 2025 news report.
- We listed every NHAI contract on the stretch and opened each award letter. We read the price, the discount, the dates and the signature.
- We read the maintenance contract's scope and its price list item by item.
- We checked each public claim against a primary document. Where we had only a news report, we say "reported".
- For the exhibits, we searched each document for the exact words and highlighted them in yellow. For scanned letters we used optical character recognition to find the words. We changed nothing else on any page.
Checks
| Fact | Checked against | Status |
|---|---|---|
| NHAI owns and maintains the section since 2018 | NHAI posts, 19 Nov 2026 | Verified |
| BRO built the truss; 60 m, through type | NHAI post; steel contractor's portfolio | Verified Unchecked (year 2011) |
| Four-laning: EPC, ₹305 cr, 11 Mar 2015 – 28 Oct 2016 | NHAI Project Information, UPC N/05012/02002/PB | Verified |
| Contract prices, discounts, letter dates, signatories | Letters of acceptance on etenders.gov.in | Verified |
| Quarterly and pre-monsoon bridge inspections required | NHAI RFP for km 50–110.72 (2024), pages 104–105 | Verified |
| No truss repair item; joints = 0.54% of estimate | NHAI BOQ_247.xls (2024) | Verified |
| Sep 2025 "urgent rectification" quote | The Tribune, 20 Sep 2025 | Reported |
| Km 60.682 bridge is a different bridge | NHAI tender 47420 schedules (stream crossing, 41.5 m) | Verified |
| Collapsed bridge at km 67.5–68 | NHAI accident map; contractor's km 17.510; Tribune 2025 | Probable |
| No bridge inspection or audit tender on this road | Our copy of etenders.gov.in, NHAI tenders 2017 – Nov 2026 | Verified (in our copy) |
Limits
- We do not know the cause of the collapse. The facts on this page do not prove a cause.
- Our copy of etenders.gov.in may miss a tender. A missing tender in our copy is not proof that no tender exists.
- Contract terms are counted from the letter date. Real start dates and extensions are not public.
- We use "indicator" for a fact that needs an explanation. An indicator is not proof of wrongdoing.
Corrections
Version 1 (19 Nov, 13:56) used the upload dates of the award letters, not the letter dates. It said that the current contract was awarded six months late. That was wrong. Version 2 corrected the dates. Version 3 adds the exhibits, the charts and the four-laning record.
Sources
NHAI
- NHAI Regional Office Chandigarh on X (@NHAIRO_CHD): traffic advisory and clarification, 19 Nov 2026.
- Maintenance contract, km 50–110.72 (2024): RFP_621.pdf; price list BOQ_247.xls.
- Km 60.682 bridge: Technical Schedules, GAD, technical result.
- Award lists: FY 2022-23, FY 2024-25, Balance for award, 1 March 2026.
- Award records and letters of acceptance on etenders.gov.in: 2021_NHAI_81978_1, 2022_NHAI_118523_1, 2022_NHAI_126864_1, 2022_NHAI_139559_1, 2024_NHAI_200504_1, 2025_NHAI_246021_1, 2025_NHAI_250918_1.
- NHAI Project Information, UPC N/05012/02002/PB; NHAI road-accident map layer (datalakew.nhai.gov.in).
Construction history
- Traders & Engineers Pvt Ltd: Patiala single span major PMT bridge
- The Tribune: 10 May 2005, 29 Jun 2013, 23 Jan 2014, 20 Mar 2017, 18 Apr 2017
- CPPP tender 2013_BRO_1843_1 (BRO Project Chetak, "road Patiala bypass").
The collapse and earlier repairs
- PTI via ThePrint, 19 Nov 2026
- The Tribune, 19 Nov 2026
- The Tribune, 20 Sep 2025 (joint repair)
- Punjabi Jagran, 19 Nov 2026 (Deputy Commissioner)
- ETV Bharat Punjabi, Aaj Tak, Sunday Guardian, Bombay Samachar
Rules
- IRC:SP:18-1996, Manual for Highway Bridge Maintenance Inspection, clause 4.2.
- NHAI policy circular 6.41/2025 (summary)